Last updated on September 11th, 2021 at 07:56 am
Ethiopia on Monday announced the completion of its second-year target of filling the Grand Ethiopian Renaissance Dam (GERD) reservoir on the Blue Nile River even as tensions with Egypt and Sudan have escalated.
Taking to Twitter, Seleshi Bekele Awulachew, Ethiopia’s Minister of Water, Irrigation, and Energy, announced that the second-year filling of the dam was completed ahead of schedule as the country witnessed heavy rains in recent days.
“This year also we are experiencing extreme rainfall in the Abbay Basin(Blue Nile Basin). As a result, the GERD reservoir has filled rapidly. GERD is an Ethiopian hydropower dam and guardian infrastructure asset for the downstream countries against climate change. It is also a means to develop further and prosper together, it can never be a treat,” the minister said in his tweets.
With this development, the Ethiopian government asserted that it can now operate two turbines at the mega hydroelectric dam.
Ethiopia, Egypt, and Sudan have not been able to reach a trilateral agreement to resolve their dispute over the GERD project despite several rounds of negotiations between leaders, ministers, and experts from the three African nations over the years.
While Ethiopia has maintained that the dam will boost its developmental projects and standard of living for the citizens, Egypt and Sudan have expressed their disagreement with the project. The two downstream countries have stated that the dam would affect their share of the river waters.
READMORE: River Nile dam & growing strategic ties between Egypt & Sub-Saharan countries
Egyptian President Abdel Fattah al-Sisi also lashed out at the Ethiopian government over the filling of the dam. He further called on international intervention into the dispute to safeguard his country’s rights in the river water.
Last week, Egypt and Sudan urged the UN Security Council to call for a legally binding agreement between the three nations to resolve the dispute with Ethiopia over the GERD dam. On the contrary, the Ethiopian government stated that the African Union is well-equipped to solve the matter and is ably facilitating the negotiations.
“Ethiopia believes an agreement is within reach, given the necessary political will and the commitment to negotiate in good faith,” Ethiopia’s water minister told the Security Council.
As per reports by Ethiopia’s state media, the $5 billion dams is about 80 percent complete and is expected to begin operation by the year 2023. It would be Africa’s largest and the world’s seventh-largest hydroelectric powerplant.
Trade between African and GCC countries stands at $ 121 billion in 2023, double of what it was in 2016.…
Family members struggling after one week after of Cyclone Chido ripped through the French island territory of Mayotte expressed helplessness…
The United Arab Emirates has launched its orphanage project in Ethiopia's Oromia region on the orders of President Sheikh Mohamed…
In just four months, 100 women have been killed, the majority by males they knew including spouses. Prime Cabinet Secretary…
The Ghanaian entertainment industry is in deep mourning following the sudden death of Bright Owusu, better known as C Confion.…
Since the beginning of December more than five hundred people have lost their lives on the nation's highways. Barbara Creecy,…
This website uses cookies.